Pre Bid Engg Services

16 Km long Zojila Tunnel (J&K)

  • 2 lane Bi-directional Tunnel on NH-1 in the state of J&K with parallel Egress tunnel , caverns and shafts . Involved 2.8 million Cum underground excavation and 50 cross passages and three deep shafts upto 480m depth.

Client

Reliance Infrastructure for NHIDCL

Z- Morh Highway Tunnel ( J&K )

  • Z Morh Tunnel on National Highway No 1 (Srinagar Sonmarg –Gumri Road) in the state of J&K 6.5 km long tunnel with parallel escape tunnel and a mid-Adit.
  • Involved 1.4 million Cum underground excavation and 25 cross passages and one Adit 0.74 km long

Client

IL&FS Transportation Network Limited

Kaithlighat Tunnel 460 m long on NH-22 (Himachal Pradesh)

Client

IL&FS Transportation Network Limited for NHAI

6 Tunnels bridges and other works on Pandoh Takoli 4 lanning NH1 project (Himachal Pradesh)

  • Length ranging from 730 m to 4166m with aggregate length of 16811m

Client

APCO , IL&FS Transportation Network Limited &for NHAI

In Progress Tunnels

Mohammad Ganj and Satbahini Railway Tunnel Project

Consultancy services for detailed design & Drawing of tunnel between Mohammad Ganj and Satbahini stations in connection with construction of 3rd line between Sonnagar-Garhwa Road Section.

Client

Rail Vikas Nigam Limited

Services

• Detailed Design Consultancy (Tunnel alignment, Design of tunnel Portal) • Preparation Feasibility Study. • Tender Preparation. • Post Contract support for tunnel construction. • Preliminary Design.

Ramban to Banihal Tunnel Project PKG-1

Detailed Design and Site Support Services, Including MEP” for Ramban to Banihal (Package-1) Four Lanning on NH 44 Project.

Client

Tata Project Ltd.

Services

• Detailed design Services for Civil works of Twin Tube Highway Tunnels 4240 m 300 m of Length: • Finalization of Tunnel Alignment • Design & Drawings of Tunnel Cross Sections, Portal Cuts, Portal Support System, NATM Support System of & final concrete linings of tunnels. • Detailed Design services for MEP works of Tunnel

Raipur –Vishakhapatnam Corridor PKG-OD7

Detail design for development of six lane Baraja –Kandili section of NH130-CD road from Km. 338+500 to Km. 342+500 – Raipur-Vishakhapatnam Economics Corridor in the state of Odisha on hybrid annuity mode (Package OD-7.

Client

Dineshchandra R. Agrawal Infracon Pvt. Ltd.

Services

• Detailed design Services for Civil works of Twin Tube Highway Tunnels 3420 m & 580m of Length: • Finalization of Tunnel Alignment & Geometric Design Plan & Profile of Tunnel . • Design & Drawings of Tunnel Cross Sections, Portal Cuts, Portal Support System, NATM Support System & final concrete linings . • Detailed Design services for MEP works of Tunnel • Detailed Design of VOP and slip roads.

Detailed Design & Supervision of 921 m long 2- lane tunnels and allied works for 4 lanning of Parwanoo- Solan Section NH5 Km 67-106 in Himachal Pradesh.

Client

GR Infraprojects for NHAI

Read More

Completed Tunnels

Chennani Nashri Highway Tunnel (J&K)

  • 9 Km long Road tunnel ( 2 lane) with parallel escape tunnel using NATM.
  • Longest road tunnel in India.
  • Involved 2.0 million Cum underground excavation and 27 cross passages.

Client

IL&FS Transportation Network Limited for NHAI.

Services

Advisory on all aspects of NATM, Construction methodology, Scheduling & Value Engineering.

Read More

Nepal : Initial design of 1.3 km long twin tunnels

  • for KNP- Madhes Expressway

Client

IL&FS Transportation Network Limited for Govt of Nepal

Services

Geological mapping and preliminary deisgn , BOQ

Tunnels on Kiratpur Ner-Chowk Highway Project Himachal Pradesh

  • Four Laning of Kiratpur to Ner-Chowk Section of NH-21 from Km 73.200 to Km 186.500 involving 6 tunnels.

Client

IL&FS Transportation Network Limited for NHAI

Services

Geological Mapping, Preliminary design & BOQ of 5 tunnels length ranging form 400m to1800m ans Aggregate 6.7 km tunnelling.

Tunnels on Udhampur-Srinagar-Baramulla Railway projects ( J&K)

  • NATM tunnels and Bridges for Kashmir railway line. Bored tunnels i.e. T -77B & 77-C along with cut & Covers & Slope protection Works

Client

Bumi Geo Engineering for IRCON International Limited

Services

Project Management services

Khambataki Ghat Project

  • Proof Consultant Services For Khambatki Ghat Project

Client

Gayatri Projects Limited

Services

Review of Geotechnical interpretative Report (GIR), tunnel design basis report and inception report including alignment report.
Checking of tunnel temporary support design and drawing of tunnel and portals including construction sequence and permanent design and drawing & Design and drawing for tunnel.

Kalanagar Mumbai: Grade separator – feasibility study for underpass tunnels.

  • Feasibility study for tunnel under-passages in c/w Grade separator using NATM and other options . 3 Underpasses two lane highway

Client

Mumbai Metropolitan Regional Authority ( MMRDA).

Copyright © 2017 Indus Consultrans pvt. ltd. All Rights Reserved