Chennani Nashri Highway Tunnel (J&K)
KUD Jammu & Kashmir Highway Tunnel
Project
DBFOT Project for Rehabilitation Strengthening and four Lanning of Chennani Nashri section of NH-1A from km 89.00 to 130.0 including Construction of 9 Km long Road tunnel ( 2 lane) with parallel escape tunnel using NATM in the state of Jammu & Kashmir .
Client
IL&FS Transportation Network Limited.
Authority:
National Highway Authority of India.
Concession Period
- EPC Cost Rs 2700 Cr
- Concession period 20 years
- Annuity project.
Project Description
- Longest road tunnel In India.
- 2 Mill cum of underground excavation
- 9.0 km long main tunnel ( Excavated Cross section: 140 sqm)
- 9.0 km long escape tunnel (Cross section: 80 sqm)
- 27 cross passages
Construction method
- NATM used for tunnelling operations from two ends of each tunnel and cross passages,
- Use of most modern Tunnelling equipment,
- Poly fibre and steel fibre application ,
Geology
- Mixed Conditions with shale clay stone etc.
- Existence of fault zones
- Squeezing conditions in middle where max overburden reached m
- 9.0 km long escape tunnel (Cross section: 80 sqm)
- 27 cross passages
Services by Indus Consultrans.
- Advisory on all aspects of NATM
- Construction methodology & Scheduling.
- Value Engineering
- Review E & M design.
- contractual issues