Underground Metro Jaipur (Chandpole to Badichaupar)

Two (2) TBM Metro Tunnels on East-West Corridor of Jaipur Metro Project (Stage 1B) at Jaipur, Rajasthan, India

Jaipur

Project

Tender Predesigns & Detailed Design of two (2) TBM Tunnels between Chandpole and Badi Chouper of the Jaipur Metro project on East-West Corridor of Jaipur Metro (Stage 1B) at Jaipur, Rajasthan, India.

Client

CEC INT’L CORP INDIA PVT. LTD.

Joint Venture

Omikron – Kappa Consulting S.A.

Construction Cost
  • Total cost : ~50,000,000 US $

Project Description
  • Two (2) single track TBM tunnels
  • Total length : ~ 2.8km
  • Cross section : 35m2 Effect. cross section : 26m2
Geology
  • Sand, Silty Sand & Silty Sand with Gravels
    Overburden for TBM: 6~12m.
Final Lining
  • Concrete M50 for TBM tunnels’ segments
  • Reinforcement Fe500D
Construction Method
  • Two (2) single track TBM tunnels : Mechanical excavation with EPB – TBM (Earth Pressure Balance –
    Tunnel Boring Machine)
Services by Indus Consultrans.
  • Preliminary Design Submissions.
  • Geotechnical Interpretation Report for the whole project.
  • Definitive Design of Sump Pit & Tunnel Drainage, design of temporary works including reaction frame.
  • Assessment and protection of Existing Building and Utilities.
  • Instrumentation systems for monitoring settlements of the ground and adjacent structures.
  • Calculation of TBM required support pressure.
  • Design of Cut & Cover Shafts and Tunnels.
  • Risk Assessment of buildings, structures and utilities due to tunnelling works.

 

Two (2) UG Metro Stations, Two (2) C&Cs and Two (2) Shafts on East-West Corridor of Jaipur Metro Project (Stage 1B) at Jaipur, Rajasthan, India

Jaipur

Project

Tender Predesign & Detailed Design of two (2) Underground Metro Stations, Choti Chouper and Badi Chouper, by Top Down Method, two (2) C&Cs and two (2) shafts for the Jaipur Metro project on East-West Corridor of Jaipur Metro (Stage 1B) at Jaipur, Rajasthan, India.

Client

CEC INT’L CORP INDIA PVT. LTD.

Joint Venture

Omikron – Kappa Consulting S.A.

Construction Cost
  • Total cost : ~50,000,000 US $
Project Schedule
  • Design – Construction : 2013 ~ 2016
Project Description
  • 7Choti Chouper underground station
    • Length : ~ 233m, Width :22.65m ~ 63.05m, Depth: ~20.00m
    • Five (5) final levels : Foundation level / Platform level / Concourse level / TV shaft level/Roof level
      Badi Chouper Station
  • Badi Chouper Station
    • Length: ~ 233m, Width: 27.95m ~ 68.35m, Depth: ~20.00m
    • Five (5) final levels: Foundation level / Platform level /
      Concourse level / TV shaft level / Roof level
  • C&Cs
    • Length: ~ 269m, Width: 12.6m, Depth:~18.00m
    • Length: ~ 110m, Width:12.6 ~23.6m, Depth:~18.00m
  • Shafts
    • Length: ~ 25.6m, Width: 24.6m, Depth:~18.00m
    • Length: ~ 25.6m, Width: 24.6m, Depth:~12.00m
Geology
  • Sand, Silty Sand & Silty Sand with Gravels
Final Lining
  • Concrete M35 for the structures, Reinforcement Fe500D
Construction Method
  • Choti & Badi Chouper Stations : Construction by Top Down method with Diaphragm Walls C&C and shafts
    with cut & cover method (piles and struts)
  • C&C and shafts with cut & cover method (piles and str
Services by Indus Consultrans.
  • Preliminary Design Submissions.
  • Geotechnical Interpretation Report for the whole project.
  • Definitive Design of Cut and Covers, Shafts, design of temporary works.
  • Ground settlement contours within the influence zone of the stations’ works.
  • Design of Secondary Structures i.e. track plinth and track concrete, emergency walkway.
  • Structural Design of the Stations with 3D analysis model.
  • Structural design of entry & exit structures, tunnel ventilation shafts, supply & exhaust vent shafts and C&C.
  • Formworks (plan views and cross sections) and reinforcement drawings for the stations, the entrances, the C&C and the shafts.
  • Details for waterproofing of various structural elements.

 